1. Pool Purchase
- Pool layout (on site)
- Sign contract
- Rescission period (3 day)
- Up front deposit $0
|
2. We Turn In For Permits Within 2 Days. Always! |
3. We Pull Permits (usually takes 1-10 days). |
4. We Start Construction Within 2 Days, After Obtaining Permits . . Always!!! |
Week 1... |
DIG............................................15% of contract due
PLUMBING
ELECTRICAL
REBAR.......................................30% of contract due |
Week 2... |
INSPECTIONS
GUNITE.....................................35% of contract due |
Week 3... |
TILE
DECKING..................................15% of contract due |
Week 4... |
EQUIPTMENT SET
PLASTER.....................................5% of contract due |
Week 5... |
|
|